Brycon completed this $1,087,000 fast-track, design-build project in 43 days to accommodate the high-technology company’s expansion and production requirements. The 48,000 square foot project included the build-out of 34 offices and conference rooms, as well as installation of Electrostatic Dissipative (ESD) flooring in the manufacturing areas.

Notable project details:

  • Fast-track schedule required multiple shifts
  • Self-performance augmented subcontractors to expedite project
  • Substantial completion in 21 days so client could occupy facility
  • High-visibility project received support from the State of New Mexico and City of Albuquerque

“Skorpios was very pleased with the quality of Brycon’s workmanship and their ability to accomplish this fast-track project.” – Elizabeth Skerry, Skorpios Project Manager